Our AI Cloud Services revenue depends on our ability to contract capacity with creditworthy customers on acceptable commercial terms, and on the continued growth of demand for AI infrastructure. We primarily contract capacity under multi-year reserved capacity arrangements that specify the amount and type of capacity, service levels, pricing, term, customer prepayments, deployment schedules and acceptance conditions. Revenue (excluding prepayments) generally commences only after applicable compute has been delivered, commissioned, placed in service and accepted (where applicable) by the relevant customer.
Our customer contracts are concentrated, and the loss of, default by, or reduction in capacity taken by any of our largest customers could materially affect our revenue and our ability to service any indebtedness incurred to finance the related infrastructure. See “Item 1A. Risk Factors.” We seek to mitigate this exposure through customer credit assessment, customer prepayments and by broadening our customer base across hyperscalers, enterprises AI developers, frontier labs, and channel partners. Diversification may reduce concentration over time but may also result in shorter contract terms, smaller individual commitments and greater variability in utilization and pricing.
Our ability to convert contracted capacity into revenue depends on delivery of capacity in accordance with contractual schedules. Each deployment requires the completion of data center construction and energization, delivery and installation of GPUs, servers, storage and networking equipment, integration and configuration of the resulting clusters, performance testing against contractual specifications, and acceptance by the customer. Revenue generally begins only upon customer acceptance, and in certain arrangements is subject to service-level credits based on uptime and other performance requirements thereafter. Delays at any stage may postpone revenue commencement and result in “delay credits”, while certain operating, financing and other costs continue to be incurred, affecting expected project returns. Failure to satisfy delivery schedules or ongoing service-level requirements may also result in significant payments under relevant customer contracts being reduced or delayed, expose us to service credits, damages or other liability, or give rise to termination rights under our customer contracts, any of which could have a material adverse impact on our business, operating results, financial condition and future prospects.
Our growth depends on our ability to secure large-scale grid-connected power, and to construct and energize data centers capable of supporting AI compute. As of June 30, 2026, we had executed grid connection agreements, letters of agreement or equivalents representing approximately 5GW of total power capacity in the United States, Canada, Spain and Asia Pacific and data center projects in varying stages of development.
Development timelines are affected by grid connection studies and approvals, transmission and substation construction, utility and transmission service provider processes, permitting, equipment lead times and construction execution. Permitting requirements, evolving regulation and community considerations may affect not only development schedules and costs but also the continued validity of the permits and grid connection rights required to operate the facility.
Once a data center is operating, our electricity costs are influenced by regional utility tariffs or wholesale market prices and, where applicable, hedging and longer-term procurement arrangements. Further, the availability of electricity and our cost of electricity may be affected by regulatory requirements and conditions that are applicable to us or data centers generally. These factors, together with data center efficiency and utilization, affect the operating costs and margins of our AI Cloud Services.
Our AI Cloud Services business requires access to successive generations of GPUs and related infrastructure. Our ability to obtain allocation of leading-edge compute on acceptable terms and timelines depends on our relationships with chipmakers and OEMs. We work closely with a diverse range of suppliers to secure access to GPUs and related infrastructure to ensure we can support our planned expansion. Tariffs, trade restrictions and supply chain disruptions may affect the availability, cost and delivery timing of GPUs, servers, networking and storage equipment and specialized electrical and cooling components.