[… 21 unchanged words …] are currently developing or may develop in the future, could be limited or otherwise adversely impacted as a result of political pressure or regulation. Government and regulatory scrutiny related to AI Cloud Services and Bitcoin mining facilities and HPC and AI services and their energy consumption and impact on the environment has increased and may continue to increase. Some governments and regulators are increasingly focused on the energy and environmental impact of data centers and Bitcoin mining activities and data centers in particular, including the impact on the electricity market that may arise from Bitcoin miners’ price responsiveness. This has led to new governmental measures regulating, restricting or prohibiting the use of electricity for data centers and Bitcoin mining activities or Bitcoin mining activities generally, and may lead to further measures with respect to Bitcoin miners and data centers more generally in any of the jurisdictions in which we operate from time to time.
For example, in December 2022, the Government of British Columbia announced a temporary 18-month suspension on new and early-stage BC Hydro connection requests from cryptocurrency mining projects, which was subsequently extended for another 18-months in June 2024. The suspension was challenged in court, but subsequently upheld by the British Columbia Court of Appeal. Additionally, in May 2024, the Government of British Columbia amended the BC Utilities Commission Act to enable the Government to enact regulations regarding public utilities’ provision of electricity service to cryptocurrency miners. While this suspension and amendment have not currently impacted our existing operations, these events demonstrate that potential policy-driven actions and future actions by Governments, or the issuance of any new legislation, government orders of regulations, may reduce the availability and/or increase the cost of electricity in the geographic locations in which our operating facilities are located or desired to be located, or could otherwise adversely impact our business.
Also, in November 2022, Governor Hochul of New York signed into law a cryptocurrency mining law that established a two-year moratorium on new or renewed permits for certain electricity-generating facilities that use fossil fuel and provide energy for proof-of-work digital asset mining operations and directed the New York State Department of Environmental Conservation to prepare a Generic Environmental Impact Statement (“GEIS”) on the environmental impact and social costs and benefits of such operations. A draft GEIS, released in May 2025 and open to public comment until September 2025, estimates the societal costs of damages from GHGs emissions between 2024 and 2050 from proof-of-work digital asset mining operations in New York State to be approximately $10.6 billion. At the federal level in the U.S., legislation has been proposed by various Senators that would require certain agencies to analyze and report on topics around energy consumption in the digital asset industry, including the type and amount of energy used for cryptocurrency mining and the effects of digital asset mining on energy prices and baseload power levels and the effect Bitcoin mining using more than 5 megawatts 5MW of power has on greenhouse gas emissions. There have also been calls by various members of Congress on the Environmental Protection Agency (“EPA”) and Department of Energy (“DOE”) to establish [… 91 unchanged words …] ERCOT relating to network planning, markets, operations, and large load interconnection processes for large loads in the ERCOT network. In addition, in 2025 the Texas government enacted Senate Bill 6, (“SB 6”), which requires the PUCT Public Utility Commission of Texas and ERCOT to create new processes and impose new requirements for the interconnection of facilities with large electrical loads of at least 75 MWs 75MW to the ERCOT system. SB Senate Bill 6 also requires security type payments as part of the initial interconnection request, and creates a new approval that is required for co-location of generation with large loads. These changes, subject to the final rules adopted by the PUCT and ERCOT and any potential judicial review, would include:
• standardization for interconnecting large loads customers in manner designed to support business development in Texas while minimizing the potential for stranded infrastructure costs and maintain system reliability;
• requiring that a large load customer who is subject to these standards contribute to the recovery of the interconnecting electric utility’s costs to interconnect the large load to a transmission system;
• codifying the process for the PUCT’s evaluation of net metering arrangements involving a large load co-located with an existing generation resource;
• directing ERCOT to develop a reliability service to competitively procure demand reductions from large load customers with a demand of at least 75 MWs to be deployed in the event of an anticipated emergency condition, which could include prohibitions on simultaneously participating in other demand response programs; and
• determining whether the current 4CP methodology used to calculate wholesale transmission rates ensures that all loads appropriately contribute to the recovery of a utility’s costs to provide access to the transmission system, and if not, determine whether alternative methods to calculate wholesale transmission rates would more appropriately assign the cost of providing access to and wholesale service from the transmission system.
These processes and requirements remain subject to rulemaking procedures and there can be no assurance as to the timing or ultimate outcome of this rulemaking process. The final regulations resulting from SB Senate Bill 6 and other processes involving PUCT Public Utility Commission of Texas and ERCOT, or any other restrictions on availability of electricity, could result in increased costs we incur in connection with interconnections to the ERCOT, cause changes to how transmission costs are allocated, reduced revenue we generate from participation in demand response or similar programs, reduce the availability of electricity, increased cost of electricity and other [… 54 unchanged words …] and/or result in more onerous disclosure and compliance burdens, and any of the foregoing could have a material adverse effect on our business, operations, prospects, financial condition and operating results.
On March 4, 2026, ERCOT published Planning Guide Revision Request (PGRR) 145 and Nodal Protocol Revision Request (NPRR) 1325 to establish Batch Zero, a one-time transitional interconnection study process, the Batch Zero Interconnection Study, for ERCOT to evaluate, on a system-wide basis, the reliability impacts of interconnection requests for loads that are 75MW or more, known as a “Large Load”, that meet certain study maturity and commitment criteria. These revisions to the ERCOT’s Planning Guide and Nodal Protocols were approved by the Public Utility Commission of Texas on June 18, 2026 with an effective date of July 11, 2026. We participated during the Batch Zero comment period by submitting public comments to ERCOT as it evaluated Batch Zero. In addition, we worked with the transmission providers for our Texas facilities, AEP Texas Inc. and Lone Star Transmission, LLC, to ensure we submitted the appropriate information for our facilities to these transmission providers in order for our facilities to participate in Batch Zero. Due to recent changes in ERCOT’s Batch Zero procedures, there may be delays in the energization of, or changes to the energization levels at, projects in Texas, including the Company's new and existing projects.
On August 3, 2026, Governor Greg Abbott of Texas issued a directive to the Public Utility Commission of Texas and ERCOT to conduct a comprehensive verification and audit of all data centers advancing through ERCOT’s interconnection process before any additional data centers are approved to move forward. On that same day, ERCOT issued a market notice regarding Batch Zero timelines and processes. By August 7, 2026, ERCOT pursuant to Batch Zero as approved by the Public Utility Commission of Texas, was to notify each interconnecting distribution service provider and transmission service provider of how any Large Load was classified in the forthcoming Batch Zero Interconnection Study. These classifications were to be: load that has already been sufficiently studied for interconnection and therefore is considered base load for the Batch Zero Interconnection Study; load that requires additional study in Batch Zero and would be considered studied load in the Batch Zero Interconnection Study; and load that has not met sufficient criteria to be included in Batch Zero and therefore will require study in a future interconnection process. ERCOT’s August 3, 2026 market notice stated that it was not going to be notifying each interconnecting distribution service provider and transmission service provider of how any Large Load was to be classified. On August 10, 2026, ERCOT filed with the Public Utility Commission of Texas its “Requests for Good Cause Exceptions Relating to Batch Zero Deadlines and Status Update on Additional Matters Including the Long-Term Load Forecast.” In these requests, ERCOT stated that it is was currently developing a comprehensive process to verify that all Large Loads included in Batch Zero to satisfy ERCOT’s planning guide and to collect additional information from developers of data centers and virtual currency mining facilities including the community impact information described in Governor Abbott’s August 3rd letter. According to ERCOT, this process is expected to take several months. We expect, based upon ERCOT’s August 10th requests to the Public Utility Commission of Texas, that once this process is completed ERCOT will then classify as described above the Large Loads submitted as part of the Batch Zero process and begin the Batch Zero Interconnection Study. On August 20, 2026, the Public Utility Commission of Texas issued an order granting ERCOT's requests for good cause exceptions providing the time requested by ERCOT to develop and implement the process to verify all Large Loads included in Batch Zero to satisfy ERCOT's planning guide and to collect the community impact information sought by Governor Abbott.
The OK Ratepayer Protection Act requires any large load customer developer (including new data centers, cryptocurrency mining operations and AI computing facilities, that contract to add 75MW or greater electric load per facility or in aggregate behind a single point of interconnection to an electric supplier’s load after the effective date) to notify adjoining landowners, county commissioners, and the Oklahoma Corporation Commission within 60 days of acquiring land for a qualifying project. HB 2992 also requires utilities to establish separate terms, conditions and tariffs for large load customers, including a minimum 10-year service term. Additionally, Oklahoma’s SB 259, which is slated to become effective on November 1, 2026, prohibits data centers from using groundwater in open-air evaporative cooling systems or other cooling technology that consumes groundwater through evaporation or discharge without recirculation. Further, to receive a groundwater permit, a data center must demonstrate that it will use low-consumptive cooling technology.
In Oklahoma, we have contracted for electric service from Public Service Company of Oklahoma (“PSO”) under a large load rate schedule. PSO’s rates are regulated by the Oklahoma Corporation Commission (“OCC”) and may only be changed through OCC proceedings, including general rate reviews and fuel and purchased power cost recovery mechanisms that pass through PSO’s underlying fuel and wholesale power costs. Accordingly, while we do not expect direct exposure to wholesale market prices in Oklahoma, changes in Southwest Power Pool wholesale energy prices, natural gas prices and PSO’s generation and purchased power costs may be passed through to us, and we do not control the timing or magnitude of any such adjustment. In addition, our arrangements may permit PSO to transition us to new or successor rate schedules approved by the OCC, and we may become subject to rates, terms and conditions of service that differ materially and adversely from those we currently anticipate. PSO has a general rate review pending before the OCC in which the design of a large load tariff applicable to customers such as us is being litigated, including a proposal to establish a separate rate class for customers adding more than 75MW of load and to require such customers to elect between self-supplied generation, utility-supplied generation, or a combination of the two. We cannot predict the outcome of that proceeding.
In Australia, the Australian Government has lodged requests with the Australian Energy Market Commission (“AEMC”) to amend the National Electricity Rules to require data center operators to pay for network costs that they cause or accelerate, together with any associated network infrastructure. The Energy and Climate Change Ministerial Council (“ECMC”) has also flagged a potential requirement for data centers to fully offset their electricity demand by investing in renewable generation and demonstrating firmed capacity. Each Australian federal, state and territory governmental agency is separately considering how to regulate data centers and address environmental and renewable energy policy concerns. Changes to law, policy or regulation could negatively impact our ability to operate our Australian operations in the way we currently anticipate, could result in materially increased regulatory or compliance costs, or adversely impact our business, financial condition and results of operations.
Although there are currently no existing federal laws or regulations that explicitly apply to digital asset mining activities as such, there are certain state regulations which vary state by state. For example, in Texas, miners with an energy capacity of more than 75MW and an interruptible load of more than 10 percent of the actual or anticipated annual peak demand of the facility are required to register their mining operations with the Public Utility Commission of Texas and report certain information to the Public Utility Commission of Texas annually, which shares that data with ERCOT. Similarly, in Oklahoma, the Data Center Customer Ratepayer Protection Act of 2026 applies to new data centers, cryptocurrency mining operations and artificial intelligence computing facilities contracting to add 75MW or more of load per facility, or in aggregate behind a single point of interconnection, after July 1, 2026, and imposes notice and documentation requirements on such customers. In addition, periodically state legislatures may pass new laws that could affect our business. See “—AI Cloud Services are energy-intensive, which may restrict the geographic locations of our operations, in particular, to locations with renewable sources of power,” and “—Government regulators and utilities may potentially restrict or delay the ability of electricity suppliers to provide electricity to Bitcoin miners or AI Cloud Service providers, including us, or Bitcoin mining or AI Cloud Services generally.”
These developments demonstrate that potential policy-driven actions and future actions by Governments, or the issuance of any new legislation, government orders or regulations, may reduce the availability and/or increase the cost of electricity in the geographic locations in which our operating facilities are located or desired to be located, and could have a materially adverse impact on our business. See also “—Risks Related to Our Business—Any electricity outage, non-supply or limitation of electricity supply, including as a result of political pressures or regulations, or increase in electricity costs may result in material impacts to our operations and financial performance.”